People in the community have ridden this route, which might offer a beneficial new network connection. Ride start and end points are anonymized for privacy.
Phase 2 (Colorado and Brunswick avenues) Week of Oct. 12 All underground utility work is complete. Crews are excavating and grading the gravel base on Brunswick Avenue in preparation for concrete curb and sidewalk installation. Week of Oct. 19 Concrete curb and sidewalk installation is expected to begin on Brunswick Avenue.
hopefully we'll get Brunswick back next week
Riders
Last Activity
Status
Pending